Windjammer Park Phase 1 Improvements Underway
07/11/2018

Please check out the Clean Water Facility website at http://www.oakharborcleanwater.org/Park for information regarding Windjammer Park Improvements!


Due to construction of the Windjammer Park Improvements (Mid-May 2018 - Late Spring 2019), large areas of the park will temporarily be unavailable to the public.

The Waterfront Trail, tidelands (beach), lagoon and ballfields will remain open.

The City has many more beautiful parks that are available.  Please visit the links below:


Thank you for your patience during construction!!

 

A drawing of the future splash park, showing families with small children on artificial rocks with fixtures that spray water into the air. A half-sunken pirate ship is included for playing. The nature playground is in the background, with three play structures.

Current Phase: Phase 1

Construction of Phase 1 park improvements has begun and is expected to be complete in late spring 2019. During this work the waterfront trail, lagoon, and ballfields will remain open. As park elements are completed, sections of the park may reopen early.

Phase 1 park elements include:

  • Splash park
  • Basketball and pickleball courts
  • New kitchen and restrooms
  • Improved landscaping and lawn areas
  • Public plaza for community events

For the most up-to-date information stay tuned for newsletters, emails, and website updates. Want to sign up for the email list? Email treatmentplant@oakharbor.org.

Phase 1 milestones:

January 2017: 165 Oak Harbor community members gave feedback on the first phase of detailed Windjammer Park design and future construction.
March 2017: Design team reached preliminary design, incorporating community feedback in multiple areas.
July 2017: Design team reached intermediate design.
August 2017: Design team asks the community for their thoughts on the updated design.
October 2017: Design team completes design of Phase 1 park improvements.
Spring 2018: Construction begins on Phase 1 park elements.

Future phases will be designed and constructed as funding is available.

The Big Picture: Windjammer Park Integration Plan

The Windjammer Park Integration Plan (WPIP) is the overarching plan that is guiding the future programming of Windjammer Park.

City Council approved the Windjammer Park Integration Plan on June 7, 2016. The plan is based on a six-month public process that gathered feedback from the community, through a Community Advisory Group and two public open houses. You can view the full plan here and the document appendices here.

Contact Us

Have questions about the Windjammer Park Integration Plan? Contact the project team at 360-914-7000 or treatmentplant@oakharbor.org.